08-23-2014 01:48 AM - edited 08-23-2014 01:49 AM
Hi,
I have two subVI's and I want to run them synchronously. I could do it but whenever one subVI is working, it's front panel becomes active. The subVI should run but I shouldn't see that it is made active. If you check out my VI, you are going to easily understand my problem. Any help would be appreciated.
08-23-2014 05:20 AM - edited 08-23-2014 05:24 AM
Hi siberrano,
at first: get rid of those local variables. ALL OF THEM! They aren't needed here!
Then you should not use sequences when you want to run things in parallel. That's contrary to DATAFLOW! You need to THINK DATAFLOW!
The subVI should run but I shouldn't see that it is made active.
Then you need to change the subVI's properties in their VI properties dialog by setting subVI properties using right click menu in the BD of the main VI…