Anomalous date-time format.

Dates get shifted by a day (see attached VI). I input seconds (since 1904) into the graph and generate the corresponding dd/mm/yy string. The graph and array of date strings start out in sync, but by the third data point they are out of sync. by a day !
0 Kudos
Message 1 of 3
(2,714 Views)
I looked at your VI. The difference between the first two elements in your array is 86400. Starting at the beginning of the array, I added 86400 to each element n and placed that value in the n+1 element. This resulted in a dates string of increasing, consecutive days. Am I missing something?
0 Kudos
Message 2 of 3
(2,714 Views)
The problem is how the data is displayed on the graph.The third element in the array which is 5/30/2003 gets plotted as 5/29/2003.
0 Kudos
Message 3 of 3