Sprint 3
KW32, 05.08.13 - 09.08.13
Developers
Adrian Schmid (100%)
Alexandre Detroz (50%)
Team Capability
22.5 Story Points / Week
Initial Sprint Backlog
U-008: Simulation, 20 Story Points
U-010: Involve Project Team, 1 Story Points
U-012: Build Prototype, 5 Story Points
U-022: Proof Of Concept, Electrical Drive Train, 5 Story Points
U-023: Set up sbRIO Eval Kit, 3 Story Points
U-024: Motor Encoders, 3 Story Points
U-025: Gyro Sensor, 5 Story Points
Total: 42Story Points
Impediments
Impediment 1: U-008: Simulation
U-008 is too big for a single user story. Changed to Epic.
New User Stories from E-008: Simulation
U-027 Understand invert pendulum model
U-028 Simulate simple balancing Robot
U-029 Simulate the real balancing robot behavior
Impediment 2: U-010: Involve Project Team
Proper Communication with all Stakeholders turns out to be much more complicated as planned..
Add U-026: Community Site
Released
U-010: Involve Project Team, 1 Story Points
U-026: NI Community Site, 3 Story Points
U-012: Build Prototype, 5 Story Points
U-022: Proof Of Concept, Electrical Drive Train, 5 Story Points
U-023: Set up sbRIO Eval Kit, 3 Story Points
U-025: Gyro Sensor, 5 Story Points
U-026: Community Site, 3 Story Points
Achieved Team Capabiltiy
25 Story Points / Week
Burndown Chart