Hello,

 

I have a simple question about the "wait for execution to complete" option by using new execution:

 

does the caller wait for the end AFTER executing the Cleanup, or just after the Main sequence?

 

regards

0 Kudos
Message 1 of 3
(3,329 Views)
Solution
Accepted by topic author mitulatbati

At the end of Cleanup at the <End Group> tag.

 