03-25-2013 04:53 AM
Hello,
I have a simple question about the "wait for execution to complete" option by using new execution:
does the caller wait for the end AFTER executing the Cleanup, or just after the Main sequence?
regards
Solved! Go to Solution.
03-25-2013 08:12 AM
At the end of Cleanup at the <End Group> tag.
Hope this helps,
03-25-2013 08:14 AM
Yes, this helps 🙂