Sorry about the previous post. Wrong key. I am wondering about which would
be more effective to use to move data from LabView 4.1 to Excel97? I am
moving large numbers of data points and placing them in different cells and
sheets within Excel. Any suggestions and some examples would be helpful.
Thanks.
0 Kudos
Message 1 of 3
(2,603 Views)
We use ActiveX to move data into Excelsheets. The application is quite
simple. Look in Examples for first Steps.

yours
Bruno

Troy schrieb in Nachricht <3936ce82@newsgroups.ni.com>...
>
>Sorry about the previous post. Wrong key. I am wondering about which
would
>be more effective to use to move data from LabView 4.1 to Excel97? I am
>moving large numbers of data points and placing them in different cells and
>sheets within Excel. Any suggestions and some examples would be helpful.
> Thanks.
0 Kudos
Message 2 of 3
(2,602 Views)
Hi Troy

I have just used ActiveX for the first time to talk to Excel, and I found it very easy with help available for the properties.

The problem that you will have, that Bruno didn't point out, is ActiveX is only available on LV5.1 for windoze.

Sorry not much help.

Tim

Bruno Hartmann wrote:

> We use ActiveX to move data into Excelsheets. The application is quite
> simple. Look in Examples for first Steps.
>
> yours
> Bruno
>
> Troy schrieb in Nachricht <3936ce82@newsgroups.ni.com>...
> >
> >Sorry about the previous post. Wrong key. I am wondering about which
> would
> >be more effective to use to move data from LabView 4.1 to Excel97? I am
> >moving large numbers of data points and placing them in different cells and
> >sheets within Exce
l. Any suggestions and some examples would be helpful.
> > Thanks.
0 Kudos