Real Time target connection lost during deployment

I am using the NI-cRIO-9030 platform with LabVIEW 2019, Real-time software in scan mode

 

I can deploy my program normally to the embedded platform and it works fine.  But at some point either later in the day or the next day I get the following when I try to deploy the same program

"Warning: Connection to the target (RT CompactRIO Target) has been lost"

 

If I make a copy of the project folder, reopen the project and redeploy it will work again, at least for a while until I have to repeat the process.  I was previously using the NI-cRIO-9073 platform and did not have this problem.  I do not believe it is my code because once deployed the program works fine and only uses about 10% of the CPU and 25% of RAM

 

Reading through some similar posts people suggested the firewall may be an issue. I tried turning off some settings and it didn't fix the problem, but I will admit that there may be firewall settings that I am unaware of. 