Sharing Hardware Resources Across Multiple DUTs in NI TestStand

Solved!
Go to solution

Hello,

 

Does NI TestStand allow sharing of hardware resources required for testing (e.g., a DAQ for voltage measurements) between multiple DUTs?

 

I am planning a production fixture to test three DUTs (PCBs) using only one DAQ. Is it possible to schedule the tests so that while DUT 1 is using the DAQ, DUTs 2 and 3 run tests that do not require this resource (i.e., parallel testing)? Once DUT 1 releases the DAQ, can the other DUTs then access it in turn?

 

Thank you,
Jakub

0 Kudos
Message 1 of 2
(235 Views)
Solution
Accepted by jakkok

There are several posibilities to achieve this in TestStand.

 

If you are using the BatchModel, you can make use of a pretty sophisticated synchronization

 

You can also use Auto-scheduling

 

For all of them, there are examples available on your installation.