How do I know when Sequence unloads?

I want to modify CVI Operator Interface for TestStand so that only one sequence is allowed to load.  If a sequence is already loaded, I want to send a command to unload, wait for some kind of acknowledgment that unload was sucessful and then load a new sequence.  I am using TestStand Ver. 3.5 and CVI ver 8.1.

Thanks
0 Kudos
Message 1 of 2
(2,702 Views)

Hi,

Do you mean Sequence File?

If you do mean the sequence, then you can set the Step properties to Load/Unload dynamicaly so that when the sequence has completed it will unload.

Regards

Ray Farmer

Regards
Ray Farmer
0 Kudos