03-19-2010 02:53 AM
2 VIs are running on the same desktop trying to acquire one on-demand sample per minute (1/min. for each VI).
The second loop that is started returns every time the error -50103:"the specified ressource isreserved. The operation as it is defined couldn't finish properly" (translation from the French version).
I am starting and stopping a task correctly with acquisition of 2 samples (1 for the CJC and the other for the type B thermocouple)
Could someone help ?
Thanks.
Solved! Go to Solution.
03-19-2010 05:13 AM