07-25-2005 12:31 PM
07-25-2005 01:07 PM
07-25-2005 07:26 PM
07-26-2005 03:19 AM
I still don't understand, but I will add a few comments.
I see one chart. It seems you want to add another chart.
What is the problem with that? Where do you want to place it?
You're building an array. Why?
Do you want 2 plots?
If so, you need to bundle the plots, not build them as an array.
Your loop runs only once. Why?
The chart is updated only after the loop finished running. Why?
You have some problems where in some cases you have an array and in others you don't. If you want to continue passing the old data, you should use a shift register.
If this didn't help, you should tell us what you are trying to accomplish.