Sprint 2 - Summary

Community Logo.png
This document was created for the myRIO Balancing Robot Project
https://decibel.ni.com/content/groups/myrio-balancing-robot
myBOT.png

Sprint 2

KW31, 29.07.13 - 02.08.13

Abstract

This Document is a short summary of development activities during Sprint 2 of myRIO Balancing Robot development.

It follows a template as described here: https://decibel.ni.com/content/docs/DOC-30567

For a description of the agile model used to develop myRIO Balancing Robot have a look here: https://decibel.ni.com/content/docs/DOC-30572

Developers

Adrian Schmid (80%)

Team Capability

12 Story Points / Week

Initial Sprint Backlog

U-002: Simulation, 20 Story Points

U-010: Involve Project Team, 1 Story Points

U-015: Competition Analysis, 5 Story Points

U-021: Develop Strategy, 8 Story Points

Total: 34 Story Points

Impediments

Released

U-015: Competition Analysis, 5 Story Points

U-022: Develop Strategy, 8 Story Points

Achieved Team Capabiltiy

13 Story Points / Week

Burndown Chart

Burndown Chart Sprint 2.png