Is there a process to have the internal Calibration Date update [using the Cal Executive software] without running the adjustment-reverify routines?

0 Kudos
Message 1 of 4
(4,619 Views)

Hi sbdata,

 

In general, unless an actual adjustment is performed, then the EEPROM is not written to and the calibration dates will remain the same. That said, if you open an external calibration and then close it, the calibrated date will be set to the current system time.

0 Kudos
Message 2 of 4
(4,598 Views)

Terminating the Calibration Executive program did not reset the external calibration [as read by Measurement & Automation Explorer, upon refresh].

0 Kudos
Message 3 of 4
(4,546 Views)

What are the exact steps that you took? Please include details and screen shots.