Hello,

i have wrote a long test sequence with teststand 3.0. For speed up this sequence i have turned of enable tracing. Now the user can`t see if the test hang´s.
Is it possible to show an statusbar simultaneously with the test in the testexec?

thankyou

Schwede
0 Kudos
Message 1 of 3
(2,778 Views)
Hi,

You could do it s few ways;

1) Make use of the Progress and Status on the Status Bar of the SeqEditer/Operator Interface. There is an example provided in the Examples folder of your TestStand under DisplayProgressAndStatus.

2) Provide a splash screen in your test which you display at the beginning of your test and remove it on completion but before you return back to Teststand.

Hope this helps.
Regards
Ray Farmer
Regards
Ray Farmer
0 Kudos
Message 2 of 3
(2,773 Views)
Hello,

I have seen this examples, works both methods side by side with the test?