NI TestStand

cancel
Showing results for 
Search instead for 
Did you mean: 

multiple reports parallel

Hello,

 

I now use teststand 2013(engine 5.1).

I have a main sequence which calls sub sequences.

Each sub sequence is a test and must run parallel, each sequence also must generate a report with a different serial number.

 

How can I achieve this. is this even possible?

 

gr,

Bart

0 Kudos
Message 1 of 3
(4,162 Views)

Hi Bart,

 

Via this link, you find a white paper. Step 4 descibes what you want to achieve. 

 

Please let me know if this helps. 

 

Regards,

Bas

0 Kudos
Message 2 of 3
(4,127 Views)

Are all of the subsequence calls to the same sequence? If so, you should be using the parallel or batch model instead of having the top level sequence.

0 Kudos
Message 3 of 3
(4,122 Views)