Dear All,

 

I am calling a sub sequence from my main sequence. I Set the property of sub sequence unload option to unload when step executes. When Execute My Main Sequence its not unloading the subsequence after execution. When I close the main sequence file then it unloads the sub sequence.

 

My Requirement is to unload the subsequence once it is finishes the execution.

 

In My subsequence file I have called “SequenceFileLoad” and “SequenceFileUnLoad” to load and unload the sequence I have put the msgbox to monitor the same.

 

Thanks & Regards,

Sathyendra N

 

0 Kudos
Message 1 of 4
(3,449 Views)

Hi,

In the Sequence Properties of the MainSequence, Uncheck the 'Optimise Non-Reentrant Calls to This Sequence'

Regards

Ray Farmer

Regards
Ray Farmer
0 Kudos
Message 2 of 4
(3,446 Views)
Hi Sathyendra,

To rephrase Ray's response:

In the Sequence Properties of the MainSequence of the SubSequence, Uncheck the 'Optimise Non-Reentrant Calls to This Sequence'

Cheers,
David Goldberg

Cheers,

David Goldberg
National Instruments
Applications Engineer
Message 3 of 4
(3,426 Views)
Hi
 
Thanks for your response David and Ray.
Its working.
 
Regards,