How to save current step position for further return ?

 
A DUT sometimes requires test operator action in order to that the testing can continue. In order to minimaze the wait time of the system when the DUT needs test operator action, it would be nice to continue to next DUT. When the test operator action is required, a notification is rised in order to alarm test operator. However, the test operator is not available 24/7. Currently the system is using a sligthly modified SequentialModel. TestStand is v3.5.
 
What I would like to do is to save that step where the DUT required test operator action in order to return that step after the following DUTs are tested and the DUT, which needed test operation action, is resolved. What would be the approach to return previously saved step ?
Furthermore, I would like to get reports for all DUTs that are finalized.
 
Regards,
Petri
 