The Current Time is Incorrect on My LabVIEW Real-Time Controller

Hello,

 

The Current Time is Incorrect on My LabVIEW Real-Time Controller.  The current date shows 4-03-70. I even went through this white paper http://digital.ni.com/public.nsf/allkb/E9D08C9F795FF49F86256F9000040DC9.  It dint help.

 

Can anyone help me with this?

0 Kudos
Message 1 of 3
(2,762 Views)

I'm pretty sure you can set the date/time in the web interface for the controller.  I don't have a cRIO here to verify.

 

There is also the Set Time.vi in the Real-Time->RT Utilities->System Configuration->Utilities palette.  It is often a good idea to use this to synchonize the RT system clock to the PC clock at the beginning of a test.


GCentral
There are only two ways to tell somebody thanks: Kudos and Marked Solutions
Unofficial Forum Rules and Guidelines
"Not that we are sufficient in ourselves to claim anything as coming from us, but our sufficiency is from God" - 2 Corinthians 3:5
Message 2 of 3
(2,751 Views)

You can also try MAX.  On my machine, when I open Remote Systems and target my PXI, there's a Time Settings tab that says "Configure the date and time settings for your target".  I seem to remember (from a few years ago, possibly with an older BIOS in my controller) that this doesn't always work ...

 